ao link
Twitter
Facebook
Linked In
Twitter
Facebook
Linked In

You are viewing 1 of your 1 free articles

Contractor appeals after losing court case against housing association over late payments

A contractor has applied to the Court of Appeal after it lost a court case against a housing association over late payments.

Linked InTwitterFacebookeCard
Cranes on a construction site
The contractor said the ruling would have a “trickle-down effect” of promoting late payments (picture: Yannick Pulver/Unsplash)
Sharelines

A contractor has applied to the Court of Appeal after it lost a court case against a housing association over late payments #UKhousing

Providence Building Services tried to end a contract with Hexagon Housing Association over missed payment deadlines, but the High Court ruled in the social landlord’s favour after it took legal action claiming the notice of termination was invalid. 

Providence signed a £7.2m contract with Hexagon in February 2019 to carry out building work for a 37-flat housing scheme in Purley, south London. 

When Hexagon missed the deadline for a payment of £260,000 to the contractor on 15 December 2022, Providence served a default notice against the housing association.

After Hexagon missed another payment deadline on 17 May 2023 for £360,000, the contractor issued a notice of termination to end the contract. Hexagon subsequently paid the sum claimed and began legal action, claiming the notice of termination was not valid.


READ MORE

Contractor on Barking balcony collapse promises ‘immediate action’ to tackle safety concernsContractor on Barking balcony collapse promises ‘immediate action’ to tackle safety concerns
Manchester housing staff win pay rise after eight-month talking period with contractorManchester housing staff win pay rise after eight-month talking period with contractor
Pocket Living says contractor has ‘accepted responsibility’ for fixing defective blockPocket Living says contractor has ‘accepted responsibility’ for fixing defective block

At the Technology and Construction Court in London on 7 November, deputy high court judge Adrian Williamson KC found in favour of Hexagon.

He ruled that the contractor had “a battery of weapons available” to protect its cash flow position, including a right to suspend the works, the payment of statutory interest, and the right to refer disputes to adjudication.

Therefore, the judge ruled, it was not “necessary or appropriate” for Providence to terminate the contract.

Providence has appealed the decision, arguing that it will have a “trickle-down effect” of promoting late payments and will make the final date of payment “optional”.

“It’s had a negative impact not just on us but on our supply chain as well,” Darren Tancred, managing director of Providence, told Inside Housing. “Many of the sub-contractors we use are small family firms… it was important for us that we were able to pay them.”

An appeal judge will now read the submission and decide whether it has the prospect of appeal.

The housing association is now working with other contractors to complete the works.

Kerry Heath, development and sales director at Hexagon Housing Association, said: “This case arose as the contractor were in essence trying to terminate the contract on the basis Hexagon was one day late in paying.

“The payment deadlines imposed by the Construction Act are very tight, which can on occasion create minor delay.

“This was never a case in which Hexagon wilfully sought to delay payment. We sought a declaration to that effect in an adjudication and received it. The contractor then issued proceedings in the Technology and Construction Court and the hearing took place in November.

“Again, we were successful and the contractor’s arguments were rejected. The judge held that the contractor’s attempt to terminate was unlawful.

“The contractor applied for leave to appeal from the judge but this was refused. The contractor has now applied for leave directly to the Court of Appeal. We are still awaiting the outcome of that application.

“Our primary focus is to complete the works so we can provide much-needed homes for people in housing need. We will naturally be seeking to recover from the contractor all our costs and losses.”

Providence maintained that Hexagon was 30 days late in paying, not one.

Sign up for our development and finance newsletter

A block of flats under construction
Picture: Alamy
Linked InTwitterFacebookeCard
Add New Comment
You must be logged in to comment.
By continuing to browse this site you are agreeing to the use of cookies. Browsing is anonymised until you sign up. Click for more info.
Cookie Settings