The Grenfell Tower Inquiry continued its in-depth investigation of the tower’s non-compliant smoke control system this week, with evidence from the various contractors involved in delivering it. Peter Apps reports
Let’s start with a little background. Since its construction in 1974, Grenfell Tower had been fitted with a smoke control system.
These were essentially four chimneys running through every residential floor of the tower, with vents on each landing. The idea is that in a fire, these vents open on the fire floor and stay closed everywhere else, with the smoke funnelling out through the chimneys instead of spreading around the building.
The inquiry has already learned that this system went wrong during a fire in 2010, when the vents on upper floors leaked smoke sucked up from a fire on the third floor, causing inhalation injuries to three residents.
An investigation led to the conclusion that the system was broken “beyond economic repair” and required replacement, with an enforcement notice served by London Fire Brigade inspectors in 2014.
But it took until 2016 for this work to actually be carried out – and it was this process and the ultimate effectiveness of it that we were investigating this week. We can begin the story in 2012.
At this point, the refurbishment of the tower was in its embryonic stages, and a design team that was working on a new school and leisure centre had been tasked with sketching out the basic ideas by building manager Kensington and Chelsea Tenant Management Organisation (KCTMO).
One of these was an engineering consultancy called Max Fordham, which was asked to review plans already prepared by another consultancy, AECOM, to upgrade the smoke system.
There was immediately a problem. The chimney shafts through which smoke was supposed to exit the building were too narrow. They had been built 0.48 square metres wide instead of the required 1.5 square metres.
The decision was taken not to remedy this defect – which would entail an enormous and disruptive construction effort – but to make the system “as good as we could within the constraints of the tower,” in the words of Matt Cross Smith, an engineer at Max Fordham at the time (pictured above).
Max Fordham picked up the AECOM designs and incorporated them into the refurbishment plans in November 2012: they would extend the vents downwards to reach the additional residential floors being added by the refurbishment and install a new mechanical extract system, using large fans to blow air through columns on one side and suck it out on the other. This is known as a ‘push/pull’ system.
Max Fordham asked a specialist contractor called PSB UK to look over the designs it had proposed.
PSB was not formally contracted at this point, but this sort of informal work was said not to be uncommon – on the understanding that it will lead to the contract to do the job later on.
However, Hugh Mahoney (pictured above), former commercial manager at the contractor, did not believe that this system would work. The narrow shafts would not be able to accommodate all the air that would be sucked in by the fans in the ‘push/pull’ system.
“It’s a bit like the old quart into a pint pot,” he said. “You’re trying to push too much air through a small hole.”
As a result of this, he did not feel that he could design a system for the tower that complied with guidance.
“You could not put forward any system that would comply with any of the guidance,” he said. “It was impossible. So therefore we, as designers, looked at it from a different direction and said, ‘Well, the spirit of the standard is to protect the stair; can we come up with an alternative design?’”
The new system he designed was bespoke: all four columns would be used to extract smoke, with air blown across the door to the stairwell.
This would – it was hoped – create the right pressure conditions for smoke in the lobbies to disperse through the open vents instead of spreading into the stairwell.
“Are you aware of any other high-rise residential building that you’ve worked on that has a smoke control system like this one?” asked counsel to the inquiry Kate Grange.
“Absolutely not,” he replied. “As I said, it was an alternative solution to try and reach the spirit of the standard, because we couldn’t achieve it in the standard way. It was impossible to put a standard system in because of the employer’s requirements.”
This new system was not perfect. One issue was that the calculations of air pressure he made for the operation of the system assumed all of the six flat entrance doors in the lobby would be closed, and the doors to the stairwell would be the only ones that opened.
An expert report by Dr Barbara Lane says that this situation never actually occurred on any floor on the night of the fire.
“Doesn’t that indicate that one single stair door being open and all other doors being closed was an unrealistic design assumption to make?” asked Ms Grange (pictured above).
Mr Mahoney said that government guidance makes this assumption and that it was “not unique to Grenfell Tower”.
“She [Dr Lane] needs to write to the Approved Document B governing body and get them to change the standards,” Mr Mahoney said.
Mr Mahoney robustly insisted that the new design constituted a “betterment” of the existing conditions, rather than a replacement system in its own right.
He said his role, as a result, was merely to ensure that the new system was an improvement on the one that had been there when he started.
In March 2014 – as the inquiry has examined at great length back in an earlier phase – Rydon was appointed lead contractor for the refurbishment job.
Rydon then appointed JS Wright as the sub-contractor responsible for the ‘mechanical and electrical’ elements of the work. And JS Wright further sub-contracted to PSB UK to work up the design proposals that it had informally prepared for Max Fordham.
To complicate the position further, JS Wright contracted another firm, RJ Electrical, to work on the actual installation of the new components. Max Fordham, meanwhile, remained involved as an advisor to KCTMO, and fire engineering consultancy Exova continued to provide ad hoc advice to the project despite not having a formal contract.
This messy web of companies made the process of tracking various decisions and responsibilities laborious and contradictory.
So who was supposed to check if the designs produced by PSB were compliant?
Alan Whyte (pictured above), senior contracts engineer at JS Wright, said the firm was merely a “middleman” that simply provided a “conduit for information from the specialist back to our client for review, approval”.
“To scrutinise a specialist sub-contractor, I think we’d have to have the in-house capability to be that specialist sub-contractor,” he said.
He said he expected “Max Fordham and building control” to pick up any defects in the design. He said his “understanding of how the chain of command worked” was that Max Fordham would seek and arrange approval from building control.
However, Mr Cross Smith (of Max Fordham) said the responsibility was JS Wright’s, claiming that following the company’s appointment, “the design of the [smoke ventilation system] was now in the hands of [JS Wright] who were taking the lead with building control”.
With regard to the negotiations with building control, in June 2015 PSB presented a technical submission for review which said that the system was “not [designed] to comply with all the requirements of the aforementioned Code of Practice”.
This worried the building control inspector, Paul Hanson. An internal PSB email shows a colleague of Mr Mahoney writing to tell him: “He wants us to basically delete it as it doesn’t tie in with what we have discussed with him. If we can respond quickly, we can avoid him rejecting the [submission].”
The line was ultimately deleted. “As I understand your evidence, [the system] wasn’t designed to comply with all the requirements of that code of practice, so why wasn’t that a statement that needed to be in there?” Ms Grange asked.
“Because we discussed it with all the relevant parties and they were happy with it. They understood after my discussions,” said Mr Mahoney.
A further problem with this system was the ‘dampers’. These are the mechanical devices that open and close to either allow smoke in on the fire floor or prevent it from seeping out higher up the building.
These come in various categories, and the type that Grenfell’s system was fitted with – fire dampers – was the lowest available standard and not designed to prevent the leakage of smoke.
Mr Mahoney said they were selected because higher quality dampers were not designed to sit within the type of vents in use on the system within Grenfell Tower.
“As the other products… on the marketplace would not fit the application that we had, and we had a betterment requirement, this was the best that we could offer, and that’s what we used,” he said.
“Did you explain that to building control?” asked Ms Grange.
“No, but they knew what they were getting,” said Mr Mahoney.
“How could you be satisfied that the dampers that you selected wouldn’t leak excessively?” asked Ms Grange.
“They would leak as much as they leaked. They were what they were. What do you mean by excessively?” said Mr Mahoney.
Asked if he had assessed the suitability of the dampers selected by his sub-contractor, Mr Whyte of JS Wright said he believed this would be done by Max Fordham.
“They were the consultant and that was my understanding of their role,” he said.
But Mr Cross Smith said he did not believe this was the case, saying he saw his role as “in general terms, keep tabs with what was going on in the project and reporting back [to KCTMO]” but he “wasn’t checking, certainly not things like the detail of the components that had been specified”.
Mr Whyte said this had “come as quite a shock” to him when he heard Mr Cross Smith’s evidence.
The evidence is that dampers did leak on the night of the fire – and from quite an early stage. Dr Lane’s expert report quoted residents who witnessed smoke leaking out of vents on the sixth, 20th and 23rd floors from as early as 20 minutes into the fire.
So what were they doing on the market and why were they sold for use on Grenfell Tower?
This question was primarily explored with Roy Jones (pictured above), technical director at Gilberts UK – the supplier that sold the ‘Series 54’ component to PSB.
In a technical explanation of the testing of the products, he explained that the ‘fire dampers’ were not supposed to limit smoke leakage and were instead supposed to retain their integrity in a fire.
The dampers were tested by Exova in October 2011, and sure enough failed the criteria for smoke leakage – both in an ambient test and during a mock fire.
“It was not an aspiration for us at the time to achieve a smoke leakage for this type of damper, it was only to achieve an integrity,” said Mr Jones.
But this is not what the team who purchased them for use on Grenfell Tower was told. Instead, the quote sent to PSB said that the dampers “lasted over 60 minutes for both fire integrity and smoke leakage but [have] no formal certification”.
“In light of your evidence and what we see on the page about the test, it’s not right, is it, that it lasted for 60 minutes in terms of smoke leakage?” asked counsel to the inquiry Alex Ustych.
“You’re absolutely correct, yes, that’s an error,” said Mr Jones.
“Do you accept that could have a misleading effect on either the purchaser or, for example, building control, who might be reviewing those additional notes as part of their assessment?” asked Mr Ustych.
Mr Jones said he did accept that, but added the “caveat” that the product was nonetheless compliant with guidance for the type of damper it was. He said the error was a result of copy and pasting an earlier mistake from a product brochure.
After the new system was installed, PSB ran checks to ensure the dampers were opening and closing correctly on each floor.
This process was led by Granville Partlow (pictured above), commissioning and sales manager at PSB. His checks involved activating the system and ensuring the dampers opened and closed on each floor as required.
This checking was partially hindered because grilles were already installed with anti-tamper screws, meaning Mr Partlow had to peer through with a torch to ensure the devices were properly closed.
He said the system was activated “probably a hundred” times to ensure it was working correctly.
But actually, what he was doing was reviewing a laptop that told him whether a signal was being sent to the dampers to close – not physically checking each time.
He said this was because “we’d have to go up and down 25 floors every time we did one damper”. So if a damper was being sent a signal but not operating, he would not have known.
He said he went up at the start and end of the day and checked all of them to ensure they were closed – and this would have alerted him to any that were jammed.
The inquiry has previously heard that concerns were raised about the system just days before the fire in June 2017, with David Hughes of Rydon alerting JS Wright to the fact that the dampers had not opened as they should have in ‘environmental mode’ (when it functions simply to ventilate the building, not as a fire safety device).
A purchase order was raised for PSB to check the system on 12 June, just two days before the fire. It was signed by Mr Whyte, but he said he was unsure precisely what had happened as a result.
Next week will begin with witnesses describing gas works to the tower. This phase of the inquiry still needs to hear from factual witnesses concerning gas, lifts and fire doors, as well as three expert witnesses: Beryl Menzies (on building control), Colin Todd (on fire risk assessment) and Dr Barbara Lane (on the entire module).
It was due to finish in the week commencing 26 July, but is around two weeks behind its original schedule.
This means it will now complete shortly after the summer break, in early September, when we will also hear closing submissions from all parties for all the evidence the inquiry has heard so far.
Investigations will then move to the London Fire Brigade and central government.
The sub-contractor responsible for the electrical work on Grenfell Tower did not check the compliance of the smoke control system it was charged with overseeing, claiming that it was merely a “middleman” in the construction project.
Grenfell smoke dampers sold with misleading testing information, inquiry hears
Devices designed to close the vents in the smoke control system at Grenfell Tower were sold with a “misleading” assurance that they had been successfully tested to prevent smoke leakage, the inquiry into the fire heard.
Grenfell smoke control system did not comply with guidance and was untested on other buildings
The smoke ventilation system used in Grenfell Tower did not comply with official guidance and had never been employed by the designers on a previous building, the inquiry into the fire heard today.
Module one: the refurbishment
Week one: A vivid picture of a broken industry
After a week of damning revelations at the opening of phase two of the Grenfell Tower Inquiry, Peter Apps recaps the key points
Click here to read the full story
Week two: What is the significance of the immunity application?
Sir Martin Moore-Bick has written to the attorney general requesting protection for those set to give evidence at the Grenfell Tower Inquiry. Peter Apps explains what the move means
Click here to read the full story
Week three: Architects of misfortune
This week saw the lead architects for the Grenfell Tower refurbishment give evidence to the inquiry. Peter Apps runs through the key points
Click here to read the full story
Week four: ‘I didn’t have any perception that it was the monster it’s become’
The architects continued to give evidence this week, outlining a lack of understanding of the fire risk posed by the cladding materials and its design. Nathaniel Barker reports
Click here to read the full story
Week five: ‘No adverse effect in relation to external fire spread’
As the Grenfell Tower Inquiry returns from its long absence, Peter Apps recaps the key points from a week of important evidence from the fire consultants to the refurbishment
Click here to read the full story
Week six: ‘I can’t recall any instance where I discussed the materials with building control’
Nathaniel Barker summarises what we learned from fire engineers Exova, architects Studio E and the early evidence from contractor Rydon
Click here to read the full story
Week seven: ‘I do not think I have ever worked with a contractor operating with this level of nonchalance’
Two key witnesses from contractor Rydon gave evidence this week. Peter Apps recaps some of the key points from a revealing week of evidence
Click here to read the full story
Week eight: ‘It haunts me that it wasn't challenged’
Four witnesses from contractor Rydon gave evidence this week. Lucie Heath recaps what we learned on the last week of evidence before the inquiry breaks for five weeks
Click here to read the full story
Week nine: ‘All I can say is you will be taken out for a very nice meal very soon’
This week the inquiry heard evidence from witnesses at Harley Facades, the sub-contractor responsible for Grenfell Tower’s cladding. Peter Apps recaps the key points
Click here to read the full story
Week 10: ‘As we all know, ACM will be gone rather quickly in a fire!’
As the Grenfell Tower Inquiry entered its 10th week, Jack Simpson recaps the key points from a week of important evidence from the refurbishment’s cladding contractor
Click here to read the full story
Week 11: ‘Did you get the impression Grenfell Tower was a guinea pig for this insulation?’
With witnesses from the cladding subcontractor, the firm which cut the deadly panels to shape and the clerk of works which inspected the job giving evidence this was week full of revelations. Peter Apps recaps the key points
Click here to read the full story
Week 12: ‘Would you accept that was a serious failing on your part?’
With the surveyor who inspected Grenfell Tower for compliance giving evidence, this was a crucial week from the inquiry. Dominic Brady and Peter Apps report
Click here to read the full story
Week 13: ‘Value for money is to be regarded as the key driver for this project’
With consultants to Kensington & Chelsea Tenant Management Organisation (KCTMO) giving evidence, attention at the Grenfell Tower Inquiry turned for this first time to the actions of the TMO and the council. Peter Apps reports
Click here to read the full story
Week 14: ‘Did it not occur to you at this point that your budget was simply too low?’
This week, for the first time in phase two, the inquiry heard from Kensington & Chelsea Tenant Management Organisation, the landlord that oversaw the fatal refurbishment of Grenfell Tower. Lucie Heath reports
Click here to read the full story
Week 15: ‘Have you ever informed the police that you destroyed documents relevant to their investigation?’
Witnesses from the Kensington and Chelsea Tenant Management Organisation (KCTMO) gave evidence for a second week, which began with a shocking revelation about withheld and destroyed evidence. Peter Apps recaps
Click here to read the full story
Week 16: ‘I conclude this was very serious evidence of professional negligence’
This week saw members of Kensington & Chelsea Tenant Management Organisation finish giving evidence, before the inquiry’s expert witnesses took the stand to make some highly critical assessments of the work they had seen before and during the refurbishment of Grenfell Tower. Jack Simpson recaps
Click here to read the full story
Grenfell Tower: a timeline of the refurbishment
Following the conclusion of module one of the Grenfell Inquiry’s second phase, Peter Apps presents a timeline of the key moments during the fatal refurbishment of the west London tower block
Click here to read the full story
Module two: the cladding products
Week 17: ‘It’s hard to make a note about this because we are not clean’
The start of the second module of the Grenfell Tower Inquiry phase two came with some huge revelations about the companies that sold the products used in the cladding system. Peter Apps reports
Click here to read the full story
Week 18: ‘It was just reckless optimism wasn't it?’
As the inquiry began cross-examining witnesses for the second module of its phase two work, the picture surrounding just how Grenfell Tower ended up wrapped in such dangerous materials became a little clearer. Nathaniel Barker was keeping an eye on proceedings
Click here to read the full story
Week 19: ‘And that was intentional, deliberate, dishonest?’
The Grenfell Tower Inquiry this week heard the shocking story of how the insulation manufacturer “manipulated” official testing and marketed its product “dishonestly”. Peter Apps tells the story
Click here to read the full story
Week 20: ‘We were outed by a consultant who we then had to fabricate a story to’
This week the inquiry investigated the actions of Kingspan – the manufacturer of one of the insulation products used in the tower’s cladding system. Dominic Brady reports
Click here to read the full story
Week 21: ‘It’s there in black and white isn't it? We see a complete absence of any consideration of life safety’
The story of insulation giant Kingspan’s testing and marketing of its combustible insulation for high rises was unpacked in minute detail this week. Peter Apps reports
Click here to read the full story
Week 22: ‘All we do is lie in here’
In the third week of evidence from insulation giant Kingspan, the inquiry continued to uncover shocking details about the firm’s behaviour both before and after the Grenfell Tower fire. Lucie Heath reports
Click here to read the full story
Week 23: ‘That would have come as an earthquake to you at the time, would it not?’
This week the inquiry took its deepest dive yet into the inner workings of the cladding manufacturer whose product has been blamed for the terrible spread of fire up Grenfell Tower. Nathaniel Barker reports
Click here to read the full story
Week 24: ‘Do you accept that Test 5B was Arconic's deadly secret’
The president of the firm that made and sold the cladding panels installed on Grenfell Tower was asked to account for the apparent concealment of “disastrous” fire tests on the product this week. Peter Apps reports
Click here to read the full story
Week 25: ‘This is quite an incredible list of omissions and missed instances, isn’t it?’
This week the Grenfell Tower Inquiry heard its first witnesses from the Building Research Establishment (BRE) - the testing house which carried out key fire tests on the Kingspan and Celotex insulation products which were later used on Grenfell Tower. Peter Apps reports.
Click here to read the full story
Week 26: 'You were taking an enormous risk, weren't you?'
Week 26 at the Grenfell Tower Inquiry was a key moment in understanding how dangerous products used on the tower came to be accepted by industry professionals. Dominic Brady reports
Click here to read the full story
Week 27: ‘What will happen if one building made out [of] PE core is in fire and will kill 60 to 70 persons?’
The most explosive evidence this week at the Grenfell Tower Inquiry came from those who did not attend, as the evidence which would have been presented to Arconic witnesses was displayed in their absence. Peter Apps reports
Click here to read the full story
Week 28: ‘This is a serious safety matter’
This week the Grenfell Tower Inquiry zeroed in on the British Board of Agrément, the body that produced “misleading” certificates which inspired trust in both the cladding and insulation used on the tower. Lucie Heath reports
Click here to read the full story
Week 29: ‘Is it true that Kingspan’s position… was to do its best to ensure that science was secretly perverted for financial gain?’
The final week in this section of the Grenfell Tower Inquiry primarily examined the attempts by insulation manufacturer Kingspan to lobby government after the fire. Peter Apps reports
Click here to read the full story
How the products used in Grenfell Tower's cladding system were tested and sold
As the section of the Grenfell Tower Inquiry examining how the products used in the cladding system were tested, marketed and sold comes to a close, Peter Apps summarises what we have learned about each of the products included in the system
Click here to read the full story
Module Three: the management of the tower
Week 30: ‘There is certainly a high probability that in the event of a fire the whole building can become an inferno’
The focus of the inquiry shifted this week to the actions of the social housing providers responsible for maintaining Grenfell Tower. Pete Apps recaps what we learned
Click here to read the full story
Week 31: ‘If we cannot get out people will die’
This week saw the former residents of Grenfell Tower enter the witness box to tell of their experiences attempting to raise complaints with the council and its managing agent. Pete Apps reports
Click here to read the full story
Week 32: ‘Let's hope our luck holds and there isn't a fire’
This week saw the return of the landlord of Grenfell Tower, Kensington and Chelsea Tenant Management Organisation (KCTMO), as senior staff members attempted to explain how vital fire safety protections at the block were allowed to fall into disrepair. Lucie Heath reports
Click here to read the full story
Week 33: ‘Isn't that a serious gap in the scope of a policy meant to safeguard vulnerable people?’
A slightly disjointed week at the Grenfell Tower inquiry saw further evidence from staff at building manager Kensington and Chelsea Tenant Management Organisation (KCTMO) interspersed with the views of a cladding expert. Peter Apps reports
Click here to read the full story
Week 34: ‘Some members of the community are doing their best to spread false information’
Jack Simpson covers all the major revelations from the past week of evidence at the Grenfell Inquiry, including evidence from Laura Johnson, director of housing at the Royal Borough of Kensington and Chelsea.
Click here to read the full story
Week 35: ‘I really didn’t like the champagne’
This week the Grenfell Tower Inquiry saw council witnesses, including former deputy leader Rock Feilding-Mellen and leader Nicholas Paget-Brown, questioned about their role in the story for the first time. Peter Apps reports
Click here to read the full story
Week 36: ‘Is that not a very incurious approach for a fire risk assessor?’
This week the Grenfell Tower Inquiry scrutinised the work of Carl Stokes, the man hired to carry out fire risk assessments for the block. Nathaniel Barker reports
Click here to read the full story
Week 37: ‘In giving that advice, weren’t you acting beyond your knowledge and expertise?’
A curtailed week at the Grenfell Tower Inquiry saw fire risk assessor Carl Stokes grilled over advice he gave regarding the tower’s cladding. Peter Apps reports
Click here to read the full story
Week 38: ‘Well it’s a bit more than that, isn’t it. He’s suggesting that you tell the LFB a lie’
The inquiry heard the mammoth cross-examination of KCTMO’s health and safety manager Janice Wray this week. Peter Apps reports
Click here to read the full story
Week 39: ‘What you said there was a grotesque understatement’
This week the inquiry continued to hear from former employees of Kensington and Chelsea Tenant Management Organisation, as well as two employees from the London Fire Brigade. Lucie Heath reports
Click here to read the full story
Week 40: ‘An exercise in concealment and half-truth’
Former KCTMO chief executive Robert Black gave his evidence to the inquiry this week and was asked to account for the various failures described over the previous six weeks. Peter Apps and Nathaniel Barker report.
Click here to read the full story
Week 41: ‘We should do nothing. This is not the sort of website we should be responding to’
This week saw the return of Robert Black, chief executive of Kensington and Chelsea Tenant Management Organisation (KCTMO), before the inquiry turned its attention to the defective smoke control system in the tower. Dominic Brady reports
Click here to read the full story
Week 42:‘They would leak as much as they leaked. They were what they were’
The Grenfell Tower Inquiry continued its in-depth investigation of the tower’s non-compliant smoke control system this week, with evidence from the various contractors involved in delivering it. Pete Apps reports
Click here to read the full story
Week 43:‘Contractors at the time were not generally aware of the importance of leaving holes unsealed’
This week the inquiry focused on two of the more overlooked areas of the Grenfell Tower fire, with evidence focusing on the gas pipelines and lifts within the west London block. It was a packed week, with five witnesses giving evidence. Jack Simpson reports
Click here to read the full story
Week 44:‘I've never seen a fully compliant firefighting lift in any local authority building, to this day actually’
This week the inquiry turn the focus onto the building’s defective lifts, with evidence from an expert, contractors who worked on them and a former engineer at KCTMO. Pete Apps reports.
Click here to read the full story
Week 45: ‘Don’t you find all this rather a surprising debate, given that the Equality Act was passed in 2010?’
The inquiry heard from expert witness Colin Todd this week, who gave his views about the work of risk assessor Carl Stokes as well as answered questions about his own guidance. Peter Apps and Nathaniel Barker report
Click here to read the full story
Week 46: ‘I think I've been very, very clear that is completely wrong’
This week the inquiry heard further expert evidence about fire risk assessor Carl Stokes’ actions, as the section of its work covering the management and maintenance of the tower concluded. Peter Apps reports
Click here to read the full story
Six key failures in the way Grenfell Tower was managed before the fire
Peter Apps recaps some of what we have learned about the actions of the Royal Borough of Kensington and Chelsea (RBKC) and Kensington and Chelsea Tenant Management Organisation (KCTMO) in the years before the fire.
Module one and two closing statements
Week 47: ‘An unedifying spectacle’
After a week of closing statements from the core participants involved in modules one and two, Lucie Heath recaps the key arguments of each group
Click here to read the full story
Module five: the fire brigade
Week 48: ‘They knew, and lives could and should have been saved’
The phase of the Grenfell Tower Inquiry examining the actions of the London Fire Brigade in the years before the fire kicked off this week with some major revelations. Peter Apps reports
Click here to read the full story
Week 49: ‘I'm not sure we've always taken every opportunity to learn as an organisation’
How the London Fire Brigade acted upon lessons from incidents in the years before the Grenfell Tower disaster came under the microscope this week at the public inquiry. Nathaniel Barker reports
Click here to read the full story
Week 50: ‘There is a culture in LFB that is very conservative. I think there is great comfort in what is familiar’
This week the inquiry heard how the London Fire Brigade (LFB) elected not to issue warnings about dangerous cladding before Grenfell and a detailed examination of its policy for checking high risk buildings. Pete Apps reports.
Click here to read the full story
Week 51:‘We teach firefighters to expect building failure’
An unusually brief week of evidence at the Grenfell Tower Inquiry explored how a fire service neighbouring London was taking a different approach to tackling blazes in high rises. Nathaniel Barker reports
Click here to read the full story
Week 52: ‘I actually think that there is a measure of incompetence at all levels’
Expert evidence concluded the current section of the inquiry with some stinging criticism of the London Fire Brigade (LFB). Pete Apps and Grainne Cuffe report.
Click here to read the full story
Module six: fire services
Week 53: ‘They make for chilling reading and harrowing listening’
The inquiry’s investigation into central government began this week with lawyers setting out their view on how and why firefighting policies failed. Peter Apps and Lucie Heath report
Click here to read the full story
Week 54: ‘Our consideration of evacuation at this time was something of a blind spot’
The development of policy on ‘stay put’, both nationally and for London, occupied the attention of the inquiry this week. Peter Apps reports
Click here to read the full story
Week 55: ‘My review is pretty scathing!’
In a week that included the 200th day of evidence in phase two of the inquiry, attention turned to the London Fire Brigade’s control room. Lucie Heath reports
Click here to read the full story
Week 56: ‘Why didn't we thump the table harder’
This week, the control room at the London Fire Brigade was examined further – both before and after the fire. Pete Apps and Lucie Heath report
Click here to read the full story
Week 57: ‘It was worse than slow, it was sluggish’
Former London Fire Brigade (LFB) commissioner Dany Cotton was the star witness this week, as the inquiry continued to delve into the brigade’s knowledge and training before the Grenfell Tower fire. Jack Simpson, Grainne Cuffe and Pete Apps report
Click here to read the full story
Week 58: ‘I don't think we deserve to ask for trust until we demonstrate different outcomes’
A current and former commissioner of the London Fire Brigade (LFB) wrapped up the inquiry’s investigation into the actions of the brigade before the fire. Grainne Cuffe and Peter Apps report.
Module six: testing and government
One of the major scandals of our time: key revelations as the Grenfell Tower Inquiry turns to government
The government was accused of “covering up” the risks of dangerous cladding as its “unbridled passion for deregulation” left it a “junior party” to the construction industry as the latest phase of the public inquiry opened today. Peter Apps summarises some of the main points
Click here to read the full story
Week 59: ‘Recent tests have apparently shown it continued to burn for 20 minutes after the flame was taken away’
After shocking opening statements, the Grenfell Tower Inquiry turned its attention to the work of Local Authority Building Control. Pete Apps reports
Click here to read the full story
Week 60: ‘You could have an exact repeat of the Dubai fire in any number of buildings in London’
The Grenfell Tower Inquiry turned its attention to the work of the National House Building Council this week, with shocking revelations about the extent of the warnings issued to central government before the fire. Peter Apps reports
Click here to read the full story
Week 61: ‘Mistakes are meant for learning, not repeating’
In the first hearings of the new year, the Grenfell Tower Inquiry heard closing statements from the firefighting section of phase two. Lucie Heath reports
Click here to read the full story
Week 62: Did it ever occur to you that this act of collaboration was, in one sense, corrupting?
The Grenfell Tower Inquiry returned to the work of the National House Building Council (NHBC) this week, with a new shocking revelation about the government’s actions in the immediate aftermath of the fire. Peter Apps reports
Click here to read the full story
Week 63: ‘It came after the general move to deregulation. So more regulation was not welcome’
The government’s focus on deregulation before the Grenfell Tower fire was placed in the spotlight this week with a series of shocking revelations about its failure to amend fire safety guidance. Pete Apps and Grainne Cuffe report
Click here to read the full story
Week 64: ‘I didn’t think ACM would be suitable for use in any high-rise buildings. I don’t think anyone did’
This week, the Building Research Establishment’s Dr Sarah Colwell gave more than three days of evidence, with some huge revelations about what was known about the dangers of aluminium composite material years before the fire and the mass confusion over the government’s building regulations. Peter Apps and Jack Simpson report
Click here to read the full story
Week 65: ‘Unless the government does something now about ACM panels, people will die’
Further evidence from the Building Research Establishment and the first government witnesses added new depth to our understanding of how warnings were missed before the Grenfell Tower fire. Peter Apps reports
Click here to read the full story
Week 66: ‘Was there a cover-up?’
The latest evidence from the Grenfell Tower Inquiry tracked the government’s failure to act on fire safety warnings right up until the months before the fire. Peter Apps and Grainne Cuffe report
Click here to read the full story
Week 67: ‘When exposed to a fire, the aluminium melts away and exposes the polyethylene. Whoosh!’
This week the inquiry heard disturbing new evidence about the failure of senior government officials to act on warnings about dangerous cladding in the years before the Grenfell Tower fire. Peter Apps reports
Click here to read the full story
Week 68: ‘Can we agree that was a pretty dangerous thing to have, all this falling on one man’s shoulders?’
Three senior civil servants gave evidence this week, including the official who had responsibility for building regulations guidance on fire safety in the years before Grenfell. Peter Apps, Lucie Heath, Stephen Delahunty and Grainne Cuffe report
Click here to read the full story
Week 69: ‘It was just unthinkable. You had the makings here of a crisis you could not comprehend’
This week, civil servant Brian Martin gave his long-awaited evidence to the Grenfell Tower Inquiry. Peter Apps reports
Click here to read the full story
Week 70: ‘Show me the bodies’
An important week at the Grenfell Tower Inquiry saw a dramatic conclusion to the mammoth cross-examination of civil servant Brian Martin, as well as the first politicians. Peter Apps and Lucie Heath report
Click here to read the full story
Week 71: ‘I have changed my schedule to fit this in. I do have an extremely busy day meeting people’
Three politicians who were responsible for building regulations before Grenfell appeared before the inquiry this week, including the former communities secretary Eric Pickles, who responded to the coroner’s letter following the Lakanal House fire. Peter Apps and Lucie Heath report
Click here to read the full story
Module Four: aftermath
Week 72: 'The system isn't broken. It was built this way'
This week the inquiry turned to the shocking story of the lack of support for bereaved and survivors in the immediate aftermath of the Grenfell Tower fire. Peter Apps, Lucie Heath, Grainne Cuffe and Jack Simpson report
Click here to read the full story
Week 73: ‘Most people would regard that as hopeless’
This week, the Grenfell Tower Inquiry heard about the Royal Borough of Kensington and Chelsea’s chaotic response in the immediate aftermath of the blaze, from the staff responsible for it. Pete Apps, Stephen Delahunty and Grainne Cuffe report
Click here to read the full story
Week 74: ‘Do you agree that RBKC was ill-prepared and incapable to meet its duties’
This week, Nicholas Holgate, former chief executive of the Royal Borough of Kensington and Chelsea, was grilled on his failure to hand over control of the aftermath of the fire, despite the borough’s lack of capacity. Peter Apps reports
Click here to read the full story
Week 75: ‘It still shocks me to the core that that’s how we treat our citizens in this country’
This week the inquiry heard witnesses from the housing management body discuss their role in the aftermath of the Grenfell Tower fire, followed by a range of witnesses from other organisations which supported the response. Peter Apps and Grainne Cuffe report
Click here to read the full story
Week 76: ‘I fear this will become our New Orleans’
This week the inquiry heard from central government figures and members of the London-wide emergency response arrangements. Peter Apps and Grainne Cuffe report
Click here to read the full story
Week 77: ‘The planning wasn’t done and there was nothing for us to be drawing on’
The Grenfell Tower Inquiry’s examination of the aftermath of the fire concluded with witnesses from central government. Peter Apps reports
Click here to read the full story
Module seven: expert evidence and closing statements
Week 78: ‘The abandonment of the ‘stay put’ strategy for high-rise residential buildings is essential’
This week the Grenfell Tower Inquiry heard a range of expert witnesses discuss their reports. Peter Apps and Grainne Cuffe report
Click here to read the full story
Week 79: ‘You could argue the system was created to enable people to circumvent the rules’
The Grenfell Tower Inquiry continued to hear expert evidence this week, with two senior figures in the world of fire safety academia criticising the government’s approach before and after the blaze. Peter Apps and Grainne Cuffe report
Click here to read the full story
Week 80: ‘The evidence points to wilful blindness and complacency towards safety’
As the inquiry moves into its final stages, lawyers for the key players gave statements about the evidence surrounding central government. Peter Apps reports
Click here to read the full story
Week 81: ‘This is Islamophobia. It’s racism. It is the elephant staring back at us in the room’
This week, closing statements covering the aftermath of the fire delivered a shocking new revelation and an expert toxicologist gave his views on the causes of the deaths. Peter Apps reports
Click here to read the full story
Module eight: further evidence relating to the deceased
Week 82: ‘Their chance to hear about the circumstances in which their loved ones died is the culmination of five years of waiting’
The Grenfell Tower Inquiry moved into its final module this week, with evidence relating to the circumstances in which the victims died. Peter Apps reports
Click here to read the full story
Week 83: ‘They died together as they lived: caring for one another’
A second week of evidence relating to the circumstances in which the victims of the fire died delivered more heartbreaking stories about their final moments. Peter Apps recaps
Click here to read the full story
Week 84: ‘Every decision affects someone who is an adored child, a beloved sister, a respected uncle, a needed mother’
The final week of oral evidence for the Grenfell Tower Inquiry’s second phase contained more heartbreaking evidence about the deaths in the tower. Peter Apps reports
Click here to read the full story
Closing statements
Week 85: ‘The merry-go-round turns still, the notes of its melody clearly audible in the last few days’
The Grenfell Tower Inquiry returned this week for closing statements from lawyers representing the bereaved and survivors and the various parties under scrutiny for the fire. Pete Apps reports.