ao link
Twitter
Facebook
Linked In
Twitter
Facebook
Linked In

Grenfell Tower Inquiry diary week 10: ‘As we all know, ACM will be gone rather quickly in a fire!’

As the Grenfell Tower Inquiry entered its 10th week, Jack Simpson recaps the key points from a week of important evidence from the refurbishment’s cladding contractor

Linked InTwitterFacebookeCard
Sharelines

As the Grenfell Tower Inquiry entered its 10th week, Jack Simpson recaps the key points from a week of important evidence from the refurbishment’s cladding contractor #UKhousing

This week, the Grenfell Tower Inquiry focused on the role of cladding contractor Harley Facades and some of the key employees involved in the refurbishment of the block were questioned.

This included estimator Mike Albiston, design manager Daniel Anketell-Jones and Kevin Lamb who was responsible for the fabrication of designs for the tower’s cladding system.

Much of the discussion over the past four days has revolved around the way in which the cladding contractor operated, the knowledge the company had on building regulations and the fire performance of materials used, as well as the use of cavity barriers to stop the fire spread throughout the building.


READ MORE

Grenfell cladding manufacturer offered combustible product unless ‘forced’ not to, inquiry hearsGrenfell cladding manufacturer offered combustible product unless ‘forced’ not to, inquiry hears
Insulation on Grenfell substituted to avoid delivery delay of just four working daysInsulation on Grenfell substituted to avoid delivery delay of just four working days
Warning of ‘weak link for fire’ missed by cladding sub-contractor at Grenfell TowerWarning of ‘weak link for fire’ missed by cladding sub-contractor at Grenfell Tower

Rewinding on the cassette issue

The week kicked-off with the inquiry taking evidence from Mr Albiston, Harley’s estimator during the Grenfell refurbishment.

His role involved costing materials and labour on projects at tender stage so that Harley could come up with a price to competitively bid for projects. He was also involved in value engineering of projects, a construction term for looking at different ways a company could make savings on a scheme either through processes, labour or, importantly in this case, materials.

Despite having worked as an estimator for years, Mr Albiston had only worked for Harley for a year and only on a handful of projects. He told the inquiry that he had never received any training or professional development at the company and kept up with developments on fire safety and building regulations by reading construction press.

Many of the questions to Mr Albiston revolved around the NBS document for the Grenfell Tower project. The NBS is the document architects send out to potential bidders which provide details on specifications, designs and materials for a project.

The Grenfell NBS document revealed that the now infamous Reynobond ACM panels were not the first choice for the tower and a zinc-based product called Proteus HR was the type of cladding panels initially preferred by Studio E. Reynobond ACM, Alucobond and another zinc-based product were listed as potential alternatives.

Evidence showed that Harley was pushing for Reynobond at an early stage.

An email from Mark Harris, commercial manager at Harley, to Studio E explained that ACM would be the contractor’s preferred material choice and said it was “tried and tested” and the company was confident of its cost base. Mr Albiston confirmed that despite there being a number of alternatives to Proteus HR being put forward, Harley only ever got a detailed quote for the Reynobond product.

When asked by counsel Richard Millett if ACM was a foregone conclusion for Harley, Mr Albiston said this was not the case and that the Proteus HR panels were still an option.

Nevertheless, Mr Albiston had set to work assessing the savings if ACM was used instead of Proteus HR and found what he thought was a £576,000 saving. However, weeks after presenting this to the project team, he realised he had omitted a number of items from his original estimate and the saving was in fact only £376,000.

It was a “basic error” which Mr Albiston said he was “horrified” by. More importantly, it put pressure on Harley to minimise the financial impact. Fixed-face panels would see Harley incur a cost of £200,000; if the contractor opted for cassette fixed panels, the hit would be reduced to £160,000.

Cassette panels are cut in a way that allows them to be hung on hidden rails, whereas face-fixed panels are essentially bolted into place with rivets. It has previously been revealed during the inquiry that ACM panels installed in cassette form had a far worse fire performance than face-fixed panels – cassette panels performed a whole three grades lower when tested.

It appears that Harley then tried keep the mistake from the architects. Responding to an email from Bruce Sounes from Studio E, which seemed to indicate that cassette-style panels would be attached, he said the comments were “interesting” and may help with Harley’s “predicament”.

A further email from Mr Harris to Simon Lawrence, contracts manager at Rydon, showed that Harley continued to push for cassette-style panels. He said that although face-fixed panels could be achieved, cassette was Harley’s preference for “lots of reasons”.

When Mr Millet asked Mr Albiston whether Harley’s desire to opt for cassette installation was driven by financial interests and whether the “lots of reasons” was referring to the money Harley would save, Mr Albiston said: “Yes.”

Daniel Anketell-Jones, design manager at Harley Facades (picture: Grenfell Tower Inquiry)
Daniel Anketell-Jones, design manager at Harley Facades (picture: Grenfell Tower Inquiry)

Insulated from knowledge

It has been a common trend of the inquiry for witnesses to apportion responsibility over certain areas of compliance to other parts of the Grenfell refurbishment supply chain. The evidence from Harley was no different.

Tuesday and Wednesday saw Mr Anketell-Jones, Harley’s design manager during the Grenfell project, questioned relentlessly by counsel Kate Grange on his knowledge of building regulations and fire safety performance.

Mr Anketell-Jones was the design manager at Grenfell, a role he said involved managing the designers to ensure they were on programme and provide some oversight of the structural work on the tower.

During the questioning on his knowledge of the materials, Mr Anketell-Jones often responded by stressing that at the time of the refurbishment, his design responsibilities stretched to only structural design and he was not educated in the areas of fire safety at the time.

Evidence was then presented to him over instances where it was suggested that he may have acquired some knowledge of building regulations and fire safety in tower blocks.

He was asked about a conference he attended, where academics gave a presentation that focused on the mechanisms of fire spread on cladded buildings and included a series of case studies on major cladding fires in the UK and abroad.

Mr Anketell-Jones said that he could not remember the talk and said that he was either out of the room or not concentrating because it was not his area of focus at Harley at the time.

Ms Grange also presented him with an email he sent to insulation manufacturers Celotex asking them for information on the testing of the Celotex RS5000 material, including how it was tested, where and how it was fixed.

Responding to this, he said he had no understanding of what the email was referring to and was merely passing on what the experts had said to him.

The Celotex RS5000 material used on Grenfell Tower was a newly launched product by the insulation manufacturer and was the first Celotex product that could be used on buildings over 18m – but, crucially, this was only when used with cement fibre cladding.

An email from Jonathan Roome, major projects and specification manager at Celotex, to Mr Anketell-Jones included an attachment with information about RS500 and when it could be used on buildings 18m and in combination with what cladding materials.

Mr Anketell-Jones said that he did not remember reading this email or the attached document and was not educated in this area.

However, despite Mr Anketell-Jones professing to having no knowledge of the fire properties of the cladding or insulation, discussion then turned to an email he sent in early 2015.

In the email, discussing the need for cavity barriers around the windows at Grenfell, Mr Anketell-Jones wrote: “There is no point in ‘fire stopping’, as we all know, the ACM will be gone rather quickly in a fire!”

When asked whether this comment about the performance of cladding was consistent with his previous evidence that he was concerned only with structural issues on Grenfell cladding, he said it was not an area he had been trained in but knew from “bits and pieces” he had picked up that ACM was a unable to resist fire for long periods.

What Mr Anketell-Jones painted a picture of was a company that was not up to date with whether the materials being used on the building were compliant.

He explained that there was never anyone designated within the company at the time of the Grenfell refurbishment that was tasked with “thinking about fire safety”. He also revealed that there had not been a technical manager – the role he said would be responsible for compliance – in place at the company between late 2012 and late 2015.

Instead he said that project managers had the responsibility of checking compliance on their projects, however this would not be through their own knowledge but instead by checking with the architect or building control.

Who’s watching the designer?

Who’s watching the designer?

Kevin Lamb, freelance designer during the Grenfell refurbishment

After four sessions of interrogating Mr Anketell-Jones, on Wednesday morning it was the turn of Mr Lamb, designer at Harley, to answer questions about his role throughout the refurbishment.

Mr Lamb was brought in by Mr Anketell-Jones on a freelance contract to help Harley, due to concerns that it did not have enough design resource to fulfil the Grenfell contract. This was highlighted in a email from commercial manager Mr Harris when commenting on the contractor’s construction team for the Grenfell ahead of Harley signing the contract. He said simply “we don’t f*cking have one” and stated that he was extremely concerned by this.

Mr Lamb had worked with Harley previously on the Chalcots Estate in 2008 and was brought in on a freelance contract to fill the design gap Harley had. He admitted to the inquiry that his expertise was mainly designing curtain wall and glazing systems, rather than cladding. He had not worked on a cladding project in six years.

Mr Lamb’s recruitment involved a phone call from Mr Anketell-Jones and a face-to-face meeting with him and Harley managing director Ray Bailey. There was no formal interview and no check of his qualifications. Mr Lamb was paid £10,572 for his services.

But the understanding of Mr Lamb’s role differs between Harley and Mr Lamb himself. According to Mr Anketell-Jones, Mr Lamb was brought in as lead designer and would be taking responsibility for the designs.

Mr Anketell-Jones said that as far as he was concerned Mr Lamb was working for Harley and was working on the pretence that he was responsible for his designs and would be sending them through to Rydon and the architect.

He later admitted that there were no quality control processes in place to check Mr Lamb’s work and that it was only his role to check that Mr Lamb was working to program and deadlines.

Mr Lamb said it was his assumption that he would be closely supervised by Harley’s management and said that he would send all of his drawings through to its team to be checked, and design meetings took place regularly.

When asked whether he understood he would be getting supervision from Harley, Mr Lamb said: “Yes, you wouldn’t expect a client to employ a third-party design source and let them get on with it, that would be very dangerous indeed.”

Emails were then presented which appeared to show that Mr Anketell-Jones had seen drawings and had made some amendments to these.

However, Mr Anketell-Jones said that these would be purely structural changes and would have no influence on materials used or fire safety performance.

The question of cavity barriers

Cavity barriers took centre stage on Thursday as Mr Lamb’s design drawings came under scrutiny.

In the Grenfell Tower Inquiry phase one report, chair Sir Martin-Moore-Bick identified the lack of cavity barriers above the windows as a significant reason for why the fire could have moved out of the first flat and ignite the combustible ACM cladding panels.

During questioning, it emerged that cavity barriers were not actually included in any of the initial drawings from Mr Lamb that were presented to the architects September 2014. Mr Lamb explained that this was down to being early in the project.

However, even after architect Neil Crawford checked the drawings without cavity barriers in January 2015, there was no mention of missing cavity barriers in his annotations.

It was not until March that Mr Lamb included cavity barriers in his drawings. These included horizontal barriers at each floor level and vertical barriers up each column that supported the tower.

When asked if this showed that cavity barriers were an afterthought, Mr Lamb said: “No, not at all.”

However, even after the cavity barriers were designed in, they crucially did not include cavity barriers around the windows.

Approved Document B states that all window openings should be closed with cavity barriers, including openings around windows. Mr Lamb said during his evidence that he was aware of Approved Document B guidance around cavity barriers and considered it to “a degree” during his work on the tower.

When asked directly by Ms Grange if he was aware that not including cavity barriers around windows was a departure from what was said in Approved Document B, Mr said: “Loosely, but I was also aware that there were other routes to compliance, a fire engineered solution.”

Mr Lamb believed that despite the lack of cavity barriers potentially going against the official guidance, the expected the architect, which he understood was supported by a fire engineer, to have come up with another solution that would have meant a lack of the cavity barrier in this area was compliant. He said that there were many routes to compliance and he understood that a fire engineered solution could meet requirements of building regulations even if designed differently to Approved Document B guidance.

It is important to point out that Grenfell was not the first Harley project to be hit by a fire. In 2012, a fire hit Taplow House on the Chalcots Estate in Camden. Luckily nobody was killed and the fire was largely contained. The installation of cavity barriers, made from non-combustible Rockwool, was seen as one of the key reasons the fire was not much worse.

When asked if information or learning from the Chalcots fire had ever been passed on by Harley, both Mr Lamb and Mr Anketell-Jones said they had been told about this or been given any information on the fire.

Mr Anketell-Jones’ assessment of cavity barriers around windows on other construction projects was a cause for concern. He said he had seen cavity barriers not used on “lots and lots of projects” and said he did not think it was appreciated in the industry that you needed cavity barriers in windows for rainscreen systems as well as masonry systems.

Sign up for our weekly Grenfell Inquiry newsletter

Sign up for our weekly Grenfell Inquiry newsletter

Each week we send out a newsletter rounding up the key news from the Grenfell Inquiry, along with the headlines from the week

New to Inside Housing? Click here to register and receive the weekly newsletter straight to your inbox

Already have an account? Click here to manage your newsletters

Grenfell Tower Inquiry phase two: weekly diaries

Grenfell Tower Inquiry phase two: weekly diaries

Module one: the refurbishment

Week one: A vivid picture of a broken industry

After a week of damning revelations at the opening of phase two of the Grenfell Tower Inquiry, Peter Apps recaps the key points

Click here to read the full story

Week two: What is the significance of the immunity application?

Sir Martin Moore-Bick has written to the attorney general requesting protection for those set to give evidence at the Grenfell Tower Inquiry. Peter Apps explains what the move means

Click here to read the full story

Week three: Architects of misfortune

This week saw the lead architects for the Grenfell Tower refurbishment give evidence to the inquiry. Peter Apps runs through the key points

Click here to read the full story

Week four: ‘I didn’t have any perception that it was the monster it’s become’

The architects continued to give evidence this week, outlining a lack of understanding of the fire risk posed by the cladding materials and its design. Nathaniel Barker reports

Click here to read the full story

Week five: ‘No adverse effect in relation to external fire spread’

As the Grenfell Tower Inquiry returns from its long absence, Peter Apps recaps the key points from a week of important evidence from the fire consultants to the refurbishment

Click here to read the full story

Week six: ‘I can’t recall any instance where I discussed the materials with building control’

Nathaniel Barker summarises what we learned from fire engineers Exova, architects Studio E and the early evidence from contractor Rydon

Click here to read the full story

Week seven: ‘I do not think I have ever worked with a contractor operating with this level of nonchalance’

Two key witnesses from contractor Rydon gave evidence this week. Peter Apps recaps some of the key points from a revealing week of evidence

Click here to read the full story

Week eight: ‘It haunts me that it wasn't challenged’

Four witnesses from contractor Rydon gave evidence this week. Lucie Heath recaps what we learned on the last week of evidence before the inquiry breaks for five weeks

Click here to read the full story

Week nine: ‘All I can say is you will be taken out for a very nice meal very soon’

This week the inquiry heard evidence from witnesses at Harley Facades, the sub-contractor responsible for Grenfell Tower’s cladding. Peter Apps recaps the key points

Click here to read the full story

Week 10: ‘As we all know, ACM will be gone rather quickly in a fire!’

As the Grenfell Tower Inquiry entered its 10th week, Jack Simpson recaps the key points from a week of important evidence from the refurbishment’s cladding contractor

Click here to read the full story

Week 11: ‘Did you get the impression Grenfell Tower was a guinea pig for this insulation?’

With witnesses from the cladding subcontractor, the firm which cut the deadly panels to shape and the clerk of works which inspected the job giving evidence this was week full of revelations. Peter Apps recaps the key points

Click here to read the full story

Week 12: ‘Would you accept that was a serious failing on your part?’

With the surveyor who inspected Grenfell Tower for compliance giving evidence, this was a crucial week from the inquiry. Dominic Brady and Peter Apps report

Click here to read the full story

Week 13: ‘Value for money is to be regarded as the key driver for this project’

With consultants to Kensington & Chelsea Tenant Management Organisation (KCTMO) giving evidence, attention at the Grenfell Tower Inquiry turned for this first time to the actions of the TMO and the council. Peter Apps reports

Click here to read the full story

Week 14: ‘Did it not occur to you at this point that your budget was simply too low?’

This week, for the first time in phase two, the inquiry heard from Kensington & Chelsea Tenant Management Organisation, the landlord that oversaw the fatal refurbishment of Grenfell Tower. Lucie Heath reports

Click here to read the full story

Week 15: ‘Have you ever informed the police that you destroyed documents relevant to their investigation?’

Witnesses from the Kensington and Chelsea Tenant Management Organisation (KCTMO) gave evidence for a second week, which began with a shocking revelation about withheld and destroyed evidence. Peter Apps recaps

Click here to read the full story

Week 16: ‘I conclude this was very serious evidence of professional negligence’

This week saw members of Kensington & Chelsea Tenant Management Organisation finish giving evidence, before the inquiry’s expert witnesses took the stand to make some highly critical assessments of the work they had seen before and during the refurbishment of Grenfell Tower. Jack Simpson recaps

Click here to read the full story

Grenfell Tower: a timeline of the refurbishment

Following the conclusion of module one of the Grenfell Inquiry’s second phase, Peter Apps presents a timeline of the key moments during the fatal refurbishment of the west London tower block

Click here to read the full story

Module two: the cladding products

Week 17: ‘It’s hard to make a note about this because we are not clean’

The start of the second module of the Grenfell Tower Inquiry phase two came with some huge revelations about the companies that sold the products used in the cladding system. Peter Apps reports

Click here to read the full story

Week 18: ‘It was just reckless optimism wasn't it?’

As the inquiry began cross-examining witnesses for the second module of its phase two work, the picture surrounding just how Grenfell Tower ended up wrapped in such dangerous materials became a little clearer. Nathaniel Barker was keeping an eye on proceedings

Click here to read the full story

Week 19: ‘And that was intentional, deliberate, dishonest?’

The Grenfell Tower Inquiry this week heard the shocking story of how the insulation manufacturer “manipulated” official testing and marketed its product “dishonestly”. Peter Apps tells the story

Click here to read the full story

Week 20: ‘We were outed by a consultant who we then had to fabricate a story to’

This week the inquiry investigated the actions of Kingspan – the manufacturer of one of the insulation products used in the tower’s cladding system. Dominic Brady reports

Click here to read the full story

Week 21: ‘It’s there in black and white isn't it? We see a complete absence of any consideration of life safety’

The story of insulation giant Kingspan’s testing and marketing of its combustible insulation for high rises was unpacked in minute detail this week. Peter Apps reports

Click here to read the full story

Week 22: ‘All we do is lie in here’

In the third week of evidence from insulation giant Kingspan, the inquiry continued to uncover shocking details about the firm’s behaviour both before and after the Grenfell Tower fire. Lucie Heath reports

Click here to read the full story

Week 23: ‘That would have come as an earthquake to you at the time, would it not?’

This week the inquiry took its deepest dive yet into the inner workings of the cladding manufacturer whose product has been blamed for the terrible spread of fire up Grenfell Tower. Nathaniel Barker reports

Click here to read the full story

Week 24: ‘Do you accept that Test 5B was Arconic's deadly secret’

The president of the firm that made and sold the cladding panels installed on Grenfell Tower was asked to account for the apparent concealment of “disastrous” fire tests on the product this week. Peter Apps reports

Click here to read the full story

Week 25: ‘This is quite an incredible list of omissions and missed instances, isn’t it?’

This week the Grenfell Tower Inquiry heard its first witnesses from the Building Research Establishment (BRE) - the testing house which carried out key fire tests on the Kingspan and Celotex insulation products which were later used on Grenfell Tower. Peter Apps reports.

Click here to read the full story

Week 26: 'You were taking an enormous risk, weren't you?'

Week 26 at the Grenfell Tower Inquiry was a key moment in understanding how dangerous products used on the tower came to be accepted by industry professionals. Dominic Brady reports

Click here to read the full story

Week 27: ‘What will happen if one building made out [of] PE core is in fire and will kill 60 to 70 persons?’

The most explosive evidence this week at the Grenfell Tower Inquiry came from those who did not attend, as the evidence which would have been presented to Arconic witnesses was displayed in their absence. Peter Apps reports

Click here to read the full story

Week 28: ‘This is a serious safety matter’

This week the Grenfell Tower Inquiry zeroed in on the British Board of Agrément, the body that produced “misleading” certificates which inspired trust in both the cladding and insulation used on the tower. Lucie Heath reports

Click here to read the full story

Week 29:  ‘Is it true that Kingspan’s position… was to do its best to ensure that science was secretly perverted for financial gain?’

The final week in this section of the Grenfell Tower Inquiry primarily examined the attempts by insulation manufacturer Kingspan to lobby government after the fire. Peter Apps reports

Click here to read the full story

How the products used in Grenfell Tower's cladding system were tested and sold

As the section of the Grenfell Tower Inquiry examining how the products used in the cladding system were tested, marketed and sold comes to a close, Peter Apps summarises what we have learned about each of the products included in the system

Click here to read the full story

Module Three: the management of the tower

Week 30: ‘There is certainly a high probability that in the event of a fire the whole building can become an inferno’

The focus of the inquiry shifted this week to the actions of the social housing providers responsible for maintaining Grenfell Tower. Pete Apps recaps what we learned

Click here to read the full story

Week 31: ‘If we cannot get out people will die’

This week saw the former residents of Grenfell Tower enter the witness box to tell of their experiences attempting to raise complaints with the council and its managing agent. Pete Apps reports

Click here to read the full story

Week 32: ‘Let's hope our luck holds and there isn't a fire’

This week saw the return of the landlord of Grenfell Tower, Kensington and Chelsea Tenant Management Organisation (KCTMO), as senior staff members attempted to explain how vital fire safety protections at the block were allowed to fall into disrepair. Lucie Heath reports

Click here to read the full story

Week 33: ‘Isn't that a serious gap in the scope of a policy meant to safeguard vulnerable people?’

A slightly disjointed week at the Grenfell Tower inquiry saw further evidence from staff at building manager Kensington and Chelsea Tenant Management Organisation (KCTMO) interspersed with the views of a cladding expert. Peter Apps reports

Click here to read the full story

Week 34: ‘Some members of the community are doing their best to spread false information’

Jack Simpson covers all the major revelations from the past week of evidence at the Grenfell Inquiry, including evidence from Laura Johnson, director of housing at the Royal Borough of Kensington and Chelsea.

Click here to read the full story  

Week 35: ‘I really didn’t like the champagne’ 

This week the Grenfell Tower Inquiry saw council witnesses, including former deputy leader Rock Feilding-Mellen and leader Nicholas Paget-Brown, questioned about their role in the story for the first time. Peter Apps reports

Click here to read the full story

Week 36: ‘Is that not a very incurious approach for a fire risk assessor?’

This week the Grenfell Tower Inquiry scrutinised the work of Carl Stokes, the man hired to carry out fire risk assessments for the block. Nathaniel Barker reports

Click here to read the full story

Week 37: ‘In giving that advice, weren’t you acting beyond your knowledge and expertise?’

A curtailed week at the Grenfell Tower Inquiry saw fire risk assessor Carl Stokes grilled over advice he gave regarding the tower’s cladding. Peter Apps reports

Click here to read the full story

Week 38: ‘Well it’s a bit more than that, isn’t it. He’s suggesting that you tell the LFB a lie’

The inquiry heard the mammoth cross-examination of KCTMO’s health and safety manager Janice Wray this week. Peter Apps reports

Click here to read the full story

Week 39: ‘What you said there was a grotesque understatement’

This week the inquiry continued to hear from former employees of Kensington and Chelsea Tenant Management Organisation, as well as two employees from the London Fire Brigade. Lucie Heath reports

Click here to read the full story

Week 40: ‘An exercise in concealment and half-truth’

Former KCTMO chief executive Robert Black gave his evidence to the inquiry this week and was asked to account for the various failures described over the previous six weeks. Peter Apps and Nathaniel Barker report.

Click here to read the full story

Week 41: ‘We should do nothing. This is not the sort of website we should be responding to’

This week saw the return of Robert Black, chief executive of Kensington and Chelsea Tenant Management Organisation (KCTMO), before the inquiry turned its attention to the defective smoke control system in the tower. Dominic Brady reports

Click here to read the full story

Week 42:‘They would leak as much as they leaked. They were what they were’

The Grenfell Tower Inquiry continued its in-depth investigation of the tower’s non-compliant smoke control system this week, with evidence from the various contractors involved in delivering it. Pete Apps reports 

Click here to read the full story

Week 43:‘Contractors at the time were not generally aware of the importance of leaving holes unsealed’

This week the inquiry focused on two of the more overlooked areas of the Grenfell Tower fire, with evidence focusing on the gas pipelines and lifts within the west London block. It was a packed week, with five witnesses giving evidence. Jack Simpson reports

Click here to read the full story

Week 44:‘I've never seen a fully compliant firefighting lift in any local authority building, to this day actually’

This week the inquiry turn the focus onto the building’s defective lifts, with evidence from an expert, contractors who worked on them and a former engineer at KCTMO. Pete Apps reports. 

Click here to read the full story

Week 45: ‘Don’t you find all this rather a surprising debate, given that the Equality Act was passed in 2010?’

The inquiry heard from expert witness Colin Todd this week, who gave his views about the work of risk assessor Carl Stokes as well as answered questions about his own guidance. Peter Apps and Nathaniel Barker report

Click here to read the full story

Week 46: ‘I think I've been very, very clear that is completely wrong’

This week the inquiry heard further expert evidence about fire risk assessor Carl Stokes’ actions, as the section of its work covering the management and maintenance of the tower concluded. Peter Apps reports

Click here to read the full story

Six key failures in the way Grenfell Tower was managed before the fire

Peter Apps recaps some of what we have learned about the actions of the Royal Borough of Kensington and Chelsea (RBKC) and Kensington and Chelsea Tenant Management Organisation (KCTMO) in the years before the fire.

Module one and two closing statements

Week 47: ‘An unedifying spectacle’

After a week of closing statements from the core participants involved in modules one and two, Lucie Heath recaps the key arguments of each group

Click here to read the full story

Module five: the fire brigade

Week 48: ‘They knew, and lives could and should have been saved’

The phase of the Grenfell Tower Inquiry examining the actions of the London Fire Brigade in the years before the fire kicked off this week with some major revelations. Peter Apps reports

Click here to read the full story

Week 49: ‘I'm not sure we've always taken every opportunity to learn as an organisation’

How the London Fire Brigade acted upon lessons from incidents in the years before the Grenfell Tower disaster came under the microscope this week at the public inquiry. Nathaniel Barker reports

Click here to read the full story

Week 50: ‘There is a culture in LFB that is very conservative. I think there is great comfort in what is familiar’

This week the inquiry heard how the London Fire Brigade (LFB) elected not to issue warnings about dangerous cladding before Grenfell and a detailed examination of its policy for checking high risk buildings. Pete Apps reports. 

Click here to read the full story

Week 51:‘We teach firefighters to expect building failure’

An unusually brief week of evidence at the Grenfell Tower Inquiry explored how a fire service neighbouring London was taking a different approach to tackling blazes in high rises. Nathaniel Barker reports

Click here to read the full story

Week 52: ‘I actually think that there is a measure of incompetence at all levels’

Expert evidence concluded the current section of the inquiry with some stinging criticism of the London Fire Brigade (LFB). Pete Apps and Grainne Cuffe report. 

Click here to read the full story

Module six: fire services

Week 53: ‘They make for chilling reading and harrowing listening’

The inquiry’s investigation into central government began this week with lawyers setting out their view on how and why firefighting policies failed. Peter Apps and Lucie Heath report

Click here to read the full story

Week 54: ‘Our consideration of evacuation at this time was something of a blind spot’

The development of policy on ‘stay put’, both nationally and for London, occupied the attention of the inquiry this week. Peter Apps reports

Click here to read the full story

Week 55: ‘My review is pretty scathing!’

In a week that included the 200th day of evidence in phase two of the inquiry, attention turned to the London Fire Brigade’s control room. Lucie Heath reports

Click here to read the full story

Week 56: ‘Why didn't we thump the table harder’

This week, the control room at the London Fire Brigade was examined further – both before and after the fire. Pete Apps and Lucie Heath report

Click here to read the full story

Week 57: ‘It was worse than slow, it was sluggish’

Former London Fire Brigade (LFB) commissioner Dany Cotton was the star witness this week, as the inquiry continued to delve into the brigade’s knowledge and training before the Grenfell Tower fire. Jack Simpson, Grainne Cuffe and Pete Apps report

Click here to read the full story

Week 58: ‘I don't think we deserve to ask for trust until we demonstrate different outcomes’

A current and former commissioner of the London Fire Brigade (LFB) wrapped up the inquiry’s investigation into the actions of the brigade before the fire. Grainne Cuffe and Peter Apps report.

Module six: testing and government 

One of the major scandals of our time: key revelations as the Grenfell Tower Inquiry turns to government

The government was accused of “covering up” the risks of dangerous cladding as its “unbridled passion for deregulation” left it a “junior party” to the construction industry as the latest phase of the public inquiry opened today. Peter Apps summarises some of the main points

Click here to read the full story

Week 59: ‘Recent tests have apparently shown it continued to burn for 20 minutes after the flame was taken away’

After shocking opening statements, the Grenfell Tower Inquiry turned its attention to the work of Local Authority Building Control. Pete Apps reports

Click here to read the full story

Week 60: ‘You could have an exact repeat of the Dubai fire in any number of buildings in London’

The Grenfell Tower Inquiry turned its attention to the work of the National House Building Council this week, with shocking revelations about the extent of the warnings issued to central government before the fire. Peter Apps reports

Click here to read the full story

Week 61: ‘Mistakes are meant for learning, not repeating’

In the first hearings of the new year, the Grenfell Tower Inquiry heard closing statements from the firefighting section of phase two. Lucie Heath reports

Click here to read the full story

Week 62: Did it ever occur to you that this act of collaboration was, in one sense, corrupting?

The Grenfell Tower Inquiry returned to the work of the National House Building Council (NHBC) this week, with a new shocking revelation about the government’s actions in the immediate aftermath of the fire. Peter Apps reports

Click here to read the full story

Week 63: ‘It came after the general move to deregulation. So more regulation was not welcome’

The government’s focus on deregulation before the Grenfell Tower fire was placed in the spotlight this week with a series of shocking revelations about its failure to amend fire safety guidance. Pete Apps and Grainne Cuffe report

Click here to read the full story

Week 64: ‘I didn’t think ACM would be suitable for use in any high-rise buildings. I don’t think anyone did’

This week, the Building Research Establishment’s Dr Sarah Colwell gave more than three days of evidence, with some huge revelations about what was known about the dangers of aluminium composite material years before the fire and the mass confusion over the government’s building regulations. Peter Apps and Jack Simpson report

Click here to read the full story

Week 65: ‘Unless the government does something now about ACM panels, people will die’

Further evidence from the Building Research Establishment and the first government witnesses added new depth to our understanding of how warnings were missed before the Grenfell Tower fire. Peter Apps reports 

Click here to read the full story

Week 66: ‘Was there a cover-up?’

The latest evidence from the Grenfell Tower Inquiry tracked the government’s failure to act on fire safety warnings right up until the months before the fire. Peter Apps and Grainne Cuffe report

Click here to read the full story

Week 67: ‘When exposed to a fire, the aluminium melts away and exposes the polyethylene. Whoosh!’

This week the inquiry heard disturbing new evidence about the failure of senior government officials to act on warnings about dangerous cladding in the years before the Grenfell Tower fire. Peter Apps reports

Click here to read the full story

Week 68: ‘Can we agree that was a pretty dangerous thing to have, all this falling on one man’s shoulders?’

Three senior civil servants gave evidence this week, including the official who had responsibility for building regulations guidance on fire safety in the years before Grenfell. Peter Apps, Lucie Heath, Stephen Delahunty and Grainne Cuffe report

Click here to read the full story

Week 69: ‘It was just unthinkable. You had the makings here of a crisis you could not comprehend’

This week, civil servant Brian Martin gave his long-awaited evidence to the Grenfell Tower Inquiry. Peter Apps reports

Click here to read the full story

Week 70: ‘Show me the bodies’

An important week at the Grenfell Tower Inquiry saw a dramatic conclusion to the mammoth cross-examination of civil servant Brian Martin, as well as the first politicians. Peter Apps and Lucie Heath report

Click here to read the full story

Week 71: ‘I have changed my schedule to fit this in. I do have an extremely busy day meeting people’

Three politicians who were responsible for building regulations before Grenfell appeared before the inquiry this week, including the former communities secretary Eric Pickles, who responded to the coroner’s letter following the Lakanal House fire. Peter Apps and Lucie Heath report

Click here to read the full story

Module Four: aftermath

Week 72: 'The system isn't broken. It was built this way'

This week the inquiry turned to the shocking story of the lack of support for bereaved and survivors in the immediate aftermath of the Grenfell Tower fire. Peter Apps, Lucie Heath, Grainne Cuffe and Jack Simpson report

Click here to read the full story

Week 73: ‘Most people would regard that as hopeless’

This week, the Grenfell Tower Inquiry heard about the Royal Borough of Kensington and Chelsea’s chaotic response in the immediate aftermath of the blaze, from the staff responsible for it. Pete AppsStephen Delahunty and Grainne Cuffe report

Click here to read the full story

Week 74: ‘Do you agree that RBKC was ill-prepared and incapable to meet its duties’

This week, Nicholas Holgate, former chief executive of the Royal Borough of Kensington and Chelsea, was grilled on his failure to hand over control of the aftermath of the fire, despite the borough’s lack of capacity. Peter Apps reports

Click here to read the full story

Week 75: ‘It still shocks me to the core that that’s how we treat our citizens in this country’

This week the inquiry heard witnesses from the housing management body discuss their role in the aftermath of the Grenfell Tower fire, followed by a range of witnesses from other organisations which supported the response. Peter Apps and Grainne Cuffe report

Click here to read the full story

Week 76: ‘I fear this will become our New Orleans’

This week the inquiry heard from central government figures and members of the London-wide emergency response arrangements. Peter Apps and Grainne Cuffe report

Click here to read the full story

Week 77: ‘The planning wasn’t done and there was nothing for us to be drawing on’

The Grenfell Tower Inquiry’s examination of the aftermath of the fire concluded with witnesses from central government. Peter Apps reports

Click here to read the full story

Module seven: expert evidence and closing statements

Week 78: ‘The abandonment of the ‘stay put’ strategy for high-rise residential buildings is essential’

This week the Grenfell Tower Inquiry heard a range of expert witnesses discuss their reports. Peter Apps and Grainne Cuffe report

Click here to read the full story

Week 79: ‘You could argue the system was created to enable people to circumvent the rules’

The Grenfell Tower Inquiry continued to hear expert evidence this week, with two senior figures in the world of fire safety academia criticising the government’s approach before and after the blaze. Peter Apps and Grainne Cuffe report 

Click here to read the full story

Week 80: ‘The evidence points to wilful blindness and complacency towards safety’

As the inquiry moves into its final stages, lawyers for the key players gave statements about the evidence surrounding central government. Peter Apps reports

Click here to read the full story

Week 81: ‘This is Islamophobia. It’s racism. It is the elephant staring back at us in the room’

This week, closing statements covering the aftermath of the fire delivered a shocking new revelation and an expert toxicologist gave his views on the causes of the deaths. Peter Apps reports

Click here to read the full story

Module eight: further evidence relating to the deceased

Week 82: ‘Their chance to hear about the circumstances in which their loved ones died is the culmination of five years of waiting’

The Grenfell Tower Inquiry moved into its final module this week, with evidence relating to the circumstances in which the victims died. Peter Apps reports

Click here to read the full story

Week 83: ‘They died together as they lived: caring for one another’

A second week of evidence relating to the circumstances in which the victims of the fire died delivered more heartbreaking stories about their final moments. Peter Apps recaps

Click here to read the full story

Week 84: ‘Every decision affects someone who is an adored child, a beloved sister, a respected uncle, a needed mother’

The final week of oral evidence for the Grenfell Tower Inquiry’s second phase contained more heartbreaking evidence about the deaths in the tower. Peter Apps reports

Click here to read the full story

Closing statements

Week 85: ‘The merry-go-round turns still, the notes of its melody clearly audible in the last few days’

The Grenfell Tower Inquiry returned this week for closing statements from lawyers representing the bereaved and survivors and the various parties under scrutiny for the fire. Pete Apps reports.  

Click here to read the full story

Linked InTwitterFacebookeCard
Add New Comment
You must be logged in to comment.
RELATED STORIES